This
is the beginning of the "re-bar forest" that strengthens the
posts. Each of these structures contains a minimum of six vertical pieces
of re-bar strapped together by rebar about every four inches.
Each of the posts is supported by a large concrete footing...
and
the foundation joins each of the footings and posts together into a solid
structure.
Sometimes there were problems. This boulder was right
where a footing had to go. It would have
taken at least a week to get a backhoe to take it out, so one of the workers spent
several days taking it out with a hammer and chisel.